Road Resurfacing

Print
Print

The City of Sandy Springs is continuing its commitment to improving our roads with the 2015 Resurfacing Program with more than 80 streets to be resurfaced as part of the program. 

Weather permitting, work will take place during daytime hours (8 a.m.-5 p.m.). Check the list below for the latest resurfacing schedule.

Please note: streets will remain open during the work; however, please makes sure vehicles are not parked in the roadway. If you have a sprinkler system, please ensure that the system is not spraying water into the road. Expect minor delays accessing your street while crews are working.

The work is done in phases. What to Expect:
Phase 1: Notice.  Our goal is to provide at least one week's notice. The schedule takes into account weather and time to complete the roads in progress.
Phase 2: Milling. Crews mill (grind up) the old asphalt.  Following the mill process, it can take up to 7 days before the next, paving phase, to take place.
Phase 3: Paving
Phase 4: Clean Up.  Public Works crews inspect the quality of the work and the clean up the area as needed.If added housekeeping is required, it is scheduled, with the additional clean up taking place typically within three business days. 

Road Segment      Projected Start Date (Milling, followed by paving approx. two days later)

Bonnie Lane            Oct. 19
Princeton Way         Oct. 20
Dalmer Rd               Oct. 25
Northside Dr            Oct. 24
Edgewater Dr           Oct. 26
Hammond Rd          Oct. 27