logo
Rendering of New Building

Future Sandy Springs Police HQ and Municipal Court (Winter 2025)

620 Morgan Falls Road, Sandy Springs, GA 30328

Map

About the Project

The new Sandy Springs Police Department Headquarters and Municipal Court will be located at 620 Morgan Falls Road. The property totals 7.42 acres and currently consists of a single four-story office building and parking lot. The building is a brick and glass veneer and steel-frame structure containing a total of 106,678 square feet of space The building was built in 1990 and has been through one significant remodel.

The current design square footage for the Sandy Springs Police Department Headquarters and Municipal Court is 130,542, with 23,864 square feet of additional space to the existing building.

  1. Police Headquarters – 110,763 sq. ft
  2. Courthouse/Lobby Addition - 11,295 sq. ft

Sally Port Addition (external to the building) – 8,484 sq. ft.

 

Rendering of Proposed Police HQ and Municipal Court

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Project Updates 

(Project Completion March 2025)

WEEKLY REPORT OCTOBER 21, 2024 (PDF)

Current Construction Activities

pdhq1021a
pdhq1021b
pdhq1021c

THIS WEEK

Roof:

  • Louver installation @ court roof
  • Brick Ledge per RFI 128

3rd Floor:

  • Carpet / LVP install
  • Painting Electrical Room
  • Millwork
  • Electrical Devices
  • Terminations at Electrical Rooms
  • Light Fixtures
  • Dropping Ceiling Tiles
  • Hanging Hard Ceilings

2nd Floor:

  • Pulling Cable
  • Electrical Devices
  • Terminations at Electrical Rooms
  • Dropping Ceiling Tiles
  • Hanging Hard Ceilings
  •  

1st Floor:

  • Cable Tray
  • Electrical Devices
  • Terminations at Electrical Rooms
  • MEP In-Wall Rough-In at Courts
  • Haning & Finishing Drywall
  • Grilles & Diffusers

Basement:

  • Existing elevator modernization continues
  • Fire Sprinklers Mains, Branch Lines & Dropping Heads
  • Tile at Restrooms
  • Electrical Devices
  • Terminations at Electrical Rooms
  • Grilles & Diffusers

Exterior:

  • Caulking at Glazing
  • Glass Install
  • Light Poles
  • U’G Conduits for Light Poles, Cameras and Generator
  • Prepping & Pouring Seat Wall Footings
  • Site Grading
  • Flashing for Siding
  • Siding at Roof Penthouse
  • Block & Brick at Seat Walls

NEXT WEEK

Roof:

  • Removing Frames per RFI 119

3rd Floor:

  • Touching Up Exposed Ceilings & Restrooms
  • Water Heaters
  • Caulking Grid around Columns
  • Running Power to PIU’s
  • Wall Tile

2nd Floor:

  • Pulling Cable
  • Terminations at Electrical Rooms
  • Dropping Ceiling Tiles
  • Finishing Hard Ceilings
  • Prep for Flooring

1st Floor:

  • Partition Steel @ Court Restrooms
  • Cable Tray & Pulling Data Cable
  • Haning & Finishing Drywall
  • Grilles & Diffusers
  • Rough-In for Camera’s

Basement:

  • Existing Elevator Modernization
  • Fire Sprinklers Mains, Branch Lines & Dropping Heads
  • Tile at Restrooms

Exterior:

  • Metal Panels
  • Site Grading
  • Prepping & Pouring Seat Walls

Project Site Aerial View and Timelapse

 

Prior Weekly Reports (PDF)

October 21, 2024

October 15, 2024

October 7, 2024

September 23, 2024

September 16, 2024

September 9, 2024

September 3, 2024

August 26, 2024

August 19, 2024

August 12, 2024

August 5, 2024

July 29, 2024

July 22, 2024

July 15, 2024

July 8, 2024

June 24, 2024

June 17, 2024

June 10,2024

June 3, 2024

May 27, 2024

May 20, 2024

May 13, 2024

May 6, 2024

April 29, 2024

April 22, 2024

April 15, 2024

April 8, 2024

April 1, 2024

March 25, 2024

March 18, 2024

March 11, 2024

March 4, 2024

February 26, 2024

February 19, 2024

February 12, 2024

February 5, 2024

January 29, 2024

January 22,2024

January 15, 2024

Weekly Report January 8, 2024 (PDF)
Weekly Report January 1, 2024 (PDF)
Weekly Report December 25, 2023 (PDF)
Weekly Report December 18, 2023 (PDF)
Weekly Report December 11, 2023 (PDF)
Weekly Report December 4, 2023 (PDF)
Weekly Report November 27, 2023 (PDF)
Weekly Report November 13, 2023 (PDF)
Weekly Report November 6, 2023 (PDF)
Weekly Report October 30, 2023 (PDF)
Weekly Report October 23, 2023 (PDF)
Weekly Report October 16, 2023 (PDF)
Weekly Report October 9, 2023 (PDF)
Weekly Report October 2, 2023 (PDF)
Weekly Report September 25, 2023 (PDF)
Weekly Report September 18, 2023 (PDF)

Project History

July 18, 2023

During the City Council Meeting, City Council approved a variance allowing alternative fence height and materials.

Agenda Item: Request for Mayor and City Council Consideration to approve a Variance from City Development Code Section 8.2.2. Parking Lot Landscaping, 8.2.7. District Boundary Buffer Wall and 8.2.10. to Allow Alternative Fence Height and Materials, Associated with the Development of the Municipal Complex.

May 30, 2023

During the Public Facilities Authority Special Called Meeting Council approved the final design for the combined Police Headquarters, Municipal Court and Feet Maintenance Building/Site project and guaranteed maximum total project pricing $45,188,432.

Agenda Item: Request for Public Facilities Authority Consideration to Approve the Guaranteed Maximum Pricing for the Police Headquarters and Municipal Courthouse Project at 620 Morgan Falls Road and to Authorize the General Manager to Execute the Change Order to the Contract

February 7, 2023

During a Public Facilities Authority Special Called Meeting, the design development pricing for the project was approved in the amount of $50,718,125.00, and directed that design and pricing be continued to obtain GMP for the Project.

Agenda Item: Request for Public Facilities Authority Consideration to Authorize the Design Development Pricing for the Police Headquarters and Municipal Courthouse Project at 620 Morgan Falls Road, and Authorizing the General Manager to Continue the Project Design to Obtain Guaranteed Maximum Pricing for the Project, and to Move Forward with Early Release of Trades of Long Lead Time Materials

August 2, 2022

During the Public Facilities Authority Special Called Meeting, City Council approved schematic design pricing for the project in the amount of $50,532,282.00 and the continuation of design to attain Guaranteed Maximum Pricing for the Project.

Public Facilities Authority Special Called Meeting
Request for Public Facilities Authority Consideration to Approve the Schematic Design Pricing for the Police Headquarters and Municipal Courthouse Project at 620 Morgan Falls Road (Project), and to Authorize the General Manager to Continue Design to Obtain Guaranteed Maximum Pricing for the Project

September 21, 2021

The Public Facility Authority adopted a resolution approving a Contract in the amount of $985,026.00 plus 2.75% of construction cost for Construction Services between the City of Sandy Springs and Reeves Young, LLC for construction of the Police Headquarters and Municipal Courthouse.

Agenda Item: Request for Public Facilities Authority Consideration of a Resolution to Approve a Contract with Reeves Young, LLC for the Construction Manager at Risk for the Public Safety Building and Authorization for the General Manager to Execute the Contract

April 29, 2021

The City issued a purchase order to Jericho in the amount of $1,035,400.00 for design services. The design scope included considerations of new mechanical, electrical, and plumbing systems, and fire protection, where applicable. In addition, upgrades as required for Americans with Disabilities Act (ADA) compliance, current building codes, including the International Building Code, NFPA 101, and Georgia Peach Green Building Rating System were to be incorporated into the design plan. Compliance with energy efficiency and sustainable construction standards were also design imperatives.

April 7, 2021

The City conducted a procurement to identify and select a qualified construction manager at risk to construct the Project according to the design plan developed by Jericho.

Site of the Proposed Police HQ and Municipal Court

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Rendering of the main entrance to the proposed Sandy Springs Police Headquarters and Municipal Court

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Rendering of the back of the proposed Sandy Springs Police Headquarters and Municipal Court

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Skate City Springs logo on top of ice of a skating rink
City Springs Event

Skate City Springs

Wednesday, November 20
Whether you glide gracefully or bumble and tumble, the holidays are always more fun on ice! Skate to holiday music, warm up with hot cocoa, and make memories at Skate City Springs! Open November 20 - January 20; admission includes skate rental. Online reservations recommended.
View Event
Newsboys
City Springs Event

Newsboys

Saturday, November 23
With a decades-spanning career in different styles and genres, award-winning Newsboys propelled hits like “We Believe” and “Born Again” up the charts. They’ve brought their live show to the world, in constant pursuit of reinvention, inspiration, and following their calling.
View Event
Vienna Boys Choir: Christmas in Vienna
City Springs Event

Vienna Boys Choir: Christmas in Vienna

Thursday, December 19
The illustrious group of child musicians has delighted music lovers worldwide for six centuries with their purity of tone, distinctive charm and popular repertoire. Christmas in Vienna showcases their voices in Austrian folk songs, classical masterpieces and holiday favorites.
View Event